Estrella-Pantaleon Bridge ahead of schedule, set to open later this year

Department of Public Works and Highways Photo

Department of Public Works and Highways Secretary Mark A. Villar announced that come second quarter of 2021, motorists will be able to utilize the widened and modernized Estrella-Pantaleon Bridge that links Estrella Street in Makati City and Barangka Drive in Mandaluyong City.

While leading a technical inspection on Wednesday, January 6, Secretary Villar said that construction of Estrella Pantaleon Bridge is now more than 72% done and is 8% ahead of schedule.

Part of the EDSA decongestion program and funded by a grant from China, Secretary  Villar was joined in the inspection by DPWH Undersecretary for Unified Project Management Office (UPMO) Operations Emil K. Sadain, UPMO Roads Management Cluster 1 Director Virgilio Castillo, and Project Manager Melchor Kabiling.

Department of Public Works and Highways Photo

Designed to decongest Guadalupe Bridge along EDSA, the main bridge of Estrella Pantaleon is a 146.0-meter prestressed concrete girder bridge with V-shaped piers, while the approach bridge/viaduct is a 66.0-meter prestressed continuous girder bridge. The approach roads at both sides have a length of 294.46 meters.

Already completed are all bridge substructure works on abutments of both sides; piers on Makati approach as well as main bridge; as well as the V-shaped piers for the main bridge.

Also completed are concrete pouring works for four (4) segments of prestressed concrete girder in Mandaluyong side and concrete pouring works for the first lift of box girder for the approach bridge in Makati.

The project’s accelerated schedule was the result of Secretary Villar’s instruction to the DPWH-UPMO to push the construction to proceed more quickly so that the bridge can be opened for public use earlier.

Secretary Villar said that DPWH UPMO under the direction of Undersecretary Sadain is doing all necessary measures of conducting a thorough inspection from time to time for resolution of technical issues, ensure quality standards and safety and to keep up with the pandemic-related challenges and backlog.

According to Undersecretary Sadain, the DPWH UPMO Roads Management Cluster 1 is now working on the remaining civil works covering formworks and rebar installation in two (2) segments of prestressed concrete girder in Mandaluyong side and two (2) more segments in Makati side as well as for the second lift of box girder for the approach bridge in Makati side in order to complete the bridge.

Once fully completed, the motoring public can expect traffic relief by providing additional fix link and alternative route crossing the Pasig River using a new two-way four-lane bridge with a total length of 506.46 meters and width of 21.65 meters, having 3-meter sidewalks on both sides, said Undersecretary Sadain.


Stay updated with news and information from the Department of Public Works and Highways by visiting their website at dpwh.gov.ph.

Balikbayan Media Center

Balikbayan Magazine's Media Center serves an audience in 60 countries and 101 cities throughout the World to ignite, drive, and fuel the economic development, progression, and modernisation of the Philippines. Our Media Center curates only the most critical, vital, useful, entertaining, and sometimes amusing information released from both the public and private sector. Our editorial team strongly believes that a well-rounded and well-informed society is a thriving society.

Spotlighting the growth, development, and progression of the Philippines since 2009. Balikbayan Magazine is a publication of the Asian Journal Media Group.

Copyright © 2009-2023 Asian Journal Media Group.
All Rights Reserved.